Elon Musk's dated promises · 341 claims, January 2015 to October 21, 2026 · graded October 26, 2026

Elon TimePromised vs actual

Of the 250 dated promises that had come due, about one in five landed on time and in full. Among the late ones he eventually kept, the median took about twice as long as he said. Another 83 are still on the clock, and 35 of those come due by December 31, 2026.

i.Promised vs actual

112 promises he kept, eventually

Each dot is a dated promise that was eventually delivered in full: 112 of the 116 in the ledger (four with horizons under a week can't sit on a log scale). On the dashed line it arrived on time. Above it, it was late. Click any dot for the quote and its sources, filter by company, or switch on the 83 still on the clock to see how much of each one's time is used up.

2.1× as long: the median among the late promises he eventually kept (the middle half ran 1.3× to 3.5×).

Delivered at all is the good case. Of the 250 claims graded, 49 landed on time and in full, 67 arrived late, 43 were partly delivered, 50 were missed and 41 were re-dated after the deadline passed.

The pattern matters more than the headline. Promises to scale something that already worked landed on time 31% of the time (31 of 101). Promises of something never done before: 12% (18 of 149). Inside 12 months, 24% landed on time. More than two years out, 8%.

Starship to orbit was promised in less than six months on September 28, 2019. It first reached orbit on Flight 14, September 28, 2026.

ii.Still on the clock

83 promises haven't come due yet. 35 come due by December 31, 2026.

Dated promises whose deadline was still ahead when the ledger was graded. None is late yet, so none counts in the scorecard above. 36 are SpaceX, 28 Tesla, 9 xAI, 7 are forecasts about artificial intelligence in general and 3 are Neuralink. Each tile is one promise, in deadline order: click it for the quote, the time left and its date on Elon time.

About 15 of 83 would land on time if his record holds: 31% of the 25 that scale something already working, 12% of the 58 that would be firsts. About 37 would eventually arrive in full.

That is the past applied to the open list, not a forecast. Most of the open promises are firsts (Mars, robotaxis at scale, humanoid robots for sale, superhuman AI), the group with the weakest record.

"On Elon time" stretches each promise by 2.1×, the median of the late ones he kept, counted from the day he said it. It is arithmetic, not a prediction.

Not counted here: the 41 promises already past due that were given a new date. Those count as goalposts moved in the scorecard.

Next to come due

The long-dated ones

iii.How it was graded

Dated and falsifiable, or it isn't in the ledger

A claim made the ledger only if Musk tied a specific, checkable outcome to a date or a time frame, in his own words, on the record. Each one was graded against its original deadline.

Search all 341 claims, with sources and grading notes